Roadwork and construction occurs throughout the City on an intermittent basis. During these times, the City advises residents and commuters to expect minor traffic delays and parking disruptions, and to choose an alternate route if possible. Signage is posted prior to any road closures, and regular updates are provided.
We recognize the inconvenience roadwork may cause, and thank you in advance for your understanding and patience. All City roadwork is described in the table below, and shown on the map in red.
Roadwork Notices
The map shows current roadwork happening in the City, with affected areas affected indicated in red. Click on the red lines or pins for more information. Zoom in and out by using the +/ - icons.
 |
- indicates City & developer roadwork |
|
|
|
 |
- resets map size |
|
|
|
| Area |
Start |
End |
Details |
| W 3rd St (multi-use path) – between Fell Ave and Marine Dr |
April 20, 2026 |
June 19, 2026 |
Installation of energy piping to development at 705 W 3rd St resulting in the closure of the multi-use path between W 3rd St and Marine Dr. Multi-use path closure + detour; sidewalk closure & detour Traffic Impacts: During construction there will be periodic impacts to Fell Ave & 3rd St intersection during loading (9AM-3PM) Construction hours: Mon – Fri: 7AM – 6PM, Sat: 9AM-5PM |
| E 4th Ave & St Patricks Ave |
May 11, 2026 |
June 30, 2026 |
Storm main replacement. • Traffic Impacts: During construction please expect road closures, sidewalk closure, bike lane detours and parking restrictions. • Construction hours: 7AM – 5PM. • Phased road closures in effect 24/7 with local traffic only access.
|
| Lane way, North of 600–700 Block East 6th Street |
May 4, 2026 |
July 4, 2026 |
The City of North Vancouver will be installing a new storm main in the lane way, north of 600–700 block of East 6th and 7th Street. This work is part of ongoing efforts to improve drainage capacity and maintain underground infrastructure. Construction will be carried out by City crews and is scheduled to begin on Monday, May 4th, 2026. The actual completion date may vary depending on weather conditions and work progress. |
| Victory Ship Way |
June 4, 2026 |
July 19, 2026 |
Traffic Impacts: To support the flow of traffic and access for Shipyards residents and businesses, Victory Ship Way will be one-way (westbound) for the duration of the event (June 11-July 19). On peak days there will be limited road closures south of Esplanade St on Lonsdale Ave and Carrie Cates Court for safety. |
| 100 Blk E 1st - between Lonsdale and St Georges |
June 27, 2026 |
July 27, 2026 |
Traffic Impacts: 100 Blk E 1st St will be closed during event operations. No street parking or drop-offs will be permitted within the closure area between closure hours. Closure hours: 7AM – 11PM. |
| 1900 – 2300 Blocks of St. Georges Ave |
June 18, 2026 |
June 30, 2026 |
A City contractor will be restoring pavement on the 1900 – 2200 Blocks of St. Georges Ave. Work is scheduled to begin on Thursday June 18, 2026 and is anticipated to be completed in two (2) weeks. The hours of work will be from 7:00 am through to 5:00 pm daily. The actual end time may vary depending on work progress. |
| West Grand Blvd multi directional bike lane |
June 15, 2026 |
July |
Installation of conduit for street lighting, one block at a time taking approximately 22 days to complete. • Multi-directional bike lane closure + detour; sidewalk closure & detour • Traffic Impacts: Minimal impacts to traffic, bike lane will be diverted and parking will be removed along West Grand Blvd. • Construction hours: Mon – Fri: 7AM – 4PM |
| Victory Ship Way |
June 4, 2026 |
July 19, 2026 |
Traffic Impacts: To support the flow of traffic and access for Shipyards residents and businesses, Victory Ship Way will be one-way (westbound) for the duration of the event (June 11-July 19). On peak days there will be limited road closures south of Esplanade St on Lonsdale Ave and Carrie Cates Court for safety. |
| 1400-1600 Bewicke Ave & 600 W 16th St |
June 15, 2026 |
October 15, 2026 |
Traffic Impacts: Phased road closures, traffic diversions, single lane alternating traffic & parking restrictions. Bus stop closures beginning July 6th - please expect delays throughout construction. Construction hours: 7AM – 8PM Monday to Friday, 9AM – 5PM Saturday |
Road Maintenance
The City maintains approximately 130 km of streets, 42 km of lanes, 145 km of sidewalks, 52 traffic signals, and 1,700 streetlights to ensure the safe and comfortable mobility of the community. Road maintenance includes street cleaning, ice and snow control, pothole patching, traffic sign installations and replacements, line marking, vegetation control, and re-lamping of streetlights and signals as required.
In addition to routine road-related maintenance, the City repaves approximately two kilometres of streets annually, based on a computerized infrastructure management program. The City also removes and replaces approximately 1,200 m of sidewalk annually, primarily in commercial areas with high pedestrian volume.
Well-maintained roads and walkways contribute to the efficient, effective movement of people and goods, but the City also envisions a greener road ahead. Any roadway expansion will only be supported if it furthers the City's vision of a sustainable community. By optimizing the use of its existing road network, the City aims to encourage more and more people to choose alternative transportation other than the single occupant vehicle.
Contact Us
Contact the City's Engineering Department if you have any questions or concerns about road maintenance in the City, at either eng@cnv.org or 604-983-7333.